MHS
OUR STORY
  • Pohang/Gwangyang
  • 2018
  • POSCO
  • CSU, GTSU, S/L
Replacement of aging loading and unloading equipment on the pier

In order to cope with the obsolescence caused by long-term use of Pohang/Gwangyang raw material unloading facilities, we carried out a replacement installation project for unloading facilities.

No. Supply Facilities Capacity Quantity Scope of Supply Completion Remarks
1 CSU
(Continuous Ship Unloader)
2,000 T/H 1 Unit EPC 2020. 1. 31 Gwangyang Steel Mill
2 GTSU
(Grab Type Ship Unloader)
2,000 T/H 1 Unit EPC 2020. 1. 31 Pohang Steel Mill
3 S/L
(Ship Loader)
2,000 T/H 1 Unit EPC 2019. 2. 28 Gwangyang Steel Mill

1. CSU (Continuous Ship Unloader) 2,000 Ton/Hour

Flow Diagram

CSU Installation

Gwangyang CSU Unit 11

2. CSU (Continuous Ship Unloader) 2,000 Ton/Hour

Flow Diagram

Pohang GTSU Unit 16

3. S/L (Ship Loader) 2,000 Ton/Hour

Flow Diagram

S/L Assembly Work (Pohang Plant)

S/L Sea Transportation